Portfolio Credit Guarantee Facility for CMSME and Financial Inclusion Sectors under Pre/Refinance Scheme. Annex GA-Loan Detail Statement
Summary
Banks and finance companies can bring collateral-free loans under four pre/refinance schemes into a portfolio credit guarantee within a calendar-year Portfolio Guarantee Limit (PGL).
Page 1 · AnalysingGuarantee cover is up to 70% of outstanding principal per borrower, capped at 30% of the PGL or enlisted loans, whichever is lower.
Page 2 · AnalysingPFIs must send PGL demand by 15 January, reserve 10% of PGL for women entrepreneurs and report new enlistments monthly by the 15th.
Page 2 · AnalysingA 0.50% guarantee fee is paid up-front for the full tenure at enlistment, with a 1% late fee for late monthly summaries.
Page 3 · AnalysingCGD Circular No. 01/2023, CGD Circular Letter No. 01/2024 and SMESPD Circular Letter No. 06/2021 are repealed, and the policy takes effect from 1 January 2026.
Page 5 · Analysing
What has changed
Guarantee moves to a portfolio basis under a calendar-year PGL set by CGD.
Page 1 · AnalysingEarlier CGD and SMESPD credit guarantee instructions are repealed.
Page 5 · Analysing
Requirements
Sign a scheme-wise Participation Agreement with CGD: To get credit guarantee cover for collateral-free loans under the CMSME Tk 25,000 crore pre-finance scheme, the Tk 10/50/100 account holders refinance scheme, the women entrepreneurs small enterprise refinance fund and the agro-product processing refinance fund, the institution must sign a scheme-wise Participation Agreement with the Credit Guarantee Department.
Page 1 · AnalysingGuarantee for only one scheme and one loan type per borrower: A customer/entrepreneur may get credit guarantee cover under only one scheme and against only one of a working capital or a term loan/investment.
Page 1 · AnalysingNon-funded and contingent facilities are outside the guarantee: Non-funded or contingent-liability loans/investments must not be brought under this guarantee.
Page 1 · AnalysingGet CGD prior approval to enlist converted contingent liabilities: If a contingent liability turns into a funded loan (other than a forced loan/investment), it may be added to the guarantee portfolio only with prior approval from CGD.
Page 1 · AnalysingKeep guaranteed loans within the customer-level loan limits: To get guarantee cover, a customer-level loan/investment must be at least Tk 25,000 and must not exceed the scheme's maximum limit for the enterprise category set in the table; under FICGS the maximum is Tk 5 lakh for a single customer and, for group loans to groups of 2-5 members, Tk 4 lakh per member and Tk 20 lakh per group.
Page 2 · AnalysingSend the scheme-wise PGL demand to CGD by 15 January: Each Participating Financial Institution (PFI) must send its scheme-wise Portfolio Guarantee Limit (PGL) demand for the calendar year to CGD by 15 January.
Page 2 · AnalysingApply to CGD to raise the PGL once it is achieved: On achieving the set PGL, PFIs may apply to CGD to increase the limit.
Page 2 · AnalysingPGL only for PFIs with average classified loans of 20% or less: Only PFIs whose classified loan/investment ratio, averaged over 31 March, 30 June and 30 September of the year before the PGL year, is 20% or less are eligible for a PGL.
Page 2 · AnalysingReserve 10% of PGL for women entrepreneurs: For schemes other than the women entrepreneurs small enterprise refinance fund, PFIs must reserve 10% of their PGL for disbursement to women entrepreneurs.
Page 2 · AnalysingUse unused women's PGL share for others after the third quarter: Any unused part of the PGL reserved for women entrepreneurs at the end of the third quarter of the year may be used to guarantee loans to other entrepreneurs.
Page 2 · AnalysingEnlist loans after documentation under Annexures Ka and Kha: PFIs must follow their own loan/investment policy and guidelines, complete documentation according to the Credit Guarantee Registration Form (Annexure-Ka) and the Due Diligence and Documentary Checklist (Annexure-Kha), disburse the loan and then add it to the guarantee portfolio; the guarantee period starts on the disbursement date.
Page 2 · AnalysingGive each enlisted loan a unique guarantee registration number: At enlistment, PFIs must give each loan/investment a unique guarantee registration number.
Page 2 · AnalysingFollow the prescribed registration number format: The registration number must follow the format 'EDW FI ALIAS/EDW_FI_ID/Short_Title_of_CGS/PGL YEAR/Registration_Number'.
Page 2 · AnalysingSend the monthly portfolio registration summary (Annexure-Ga): PFIs must send CGD the scheme-wise Monthly Portfolio Guarantee Registration Summary for New Loan/Investment (Annexure-Ga) by the 15th of the following month.
Page 3 · AnalysingE-mail soft copies of new loan detail statements: Within the same time, PFIs must e-mail the soft copy (Excel file) of each enlisted New Loan/Investment Detail Statement listed in Annexure-Ga to [email protected].
Page 3 · AnalysingGet CGD prior approval to reschedule or restructure guaranteed term loans: PFIs must obtain prior approval from CGD before rescheduling or restructuring an enlisted term loan/investment.
Page 3 · AnalysingReport rescheduled/restructured loans in Annexure-Gha: After CGD's no-objection, PFIs must send details of rescheduled/restructured loans in the Statement of Rescheduling/Restructuring Term Loan/Investment (Annexure-Gha) to CGD in writing and as an Excel soft copy to [email protected] by the 15th of the following month; the loan stays under its original PGL and keeps its registration number.
Page 3 · AnalysingRenew guaranteed working capital loans within their tenure: An enlisted working capital loan/investment must be renewed within its existing tenure.
Page 3 · AnalysingComplete renewal of guaranteed working capital loans within 15 days: Although BRPD Circular No. 06 dated 25 June 2025 applies, the renewal process of a guaranteed working capital loan may be completed within the next 15 days.
Page 3 · AnalysingReport renewed working capital loans in Annexure-Umo: PFIs must send details of renewed working capital loans in the Statement of Renewal of Working Capital Loan/Investment (Annexure-Umo) to CGD in writing and as an Excel soft copy to [email protected] by the 15th of the following month; the loan stays under its original PGL and keeps its registration number.
Page 3 · AnalysingSubmit portfolio data online after automation: Once automation is complete, PFIs may submit the data of enlisted loans online through www.cgims.bb.org.bd.
Page 3 · AnalysingNo new guarantees while a scheme Participation Agreement is cancelled or suspended: If a PFI's participation agreement for a scheme with the SME and Special Programmes Department or the Financial Inclusion Department is cancelled or suspended, no new guarantee may be enlisted for that PFI under that scheme until the cancellation or suspension is withdrawn.
Page 3 · AnalysingInform CGD in writing when refinance is not given or is cancelled: If an enlisted loan is not included in, or loses, the related pre/refinance facility, its guarantee is treated as cancelled and the PFI must inform CGD in writing.
Page 3 · AnalysingPay the guarantee fee up-front for the full tenure at enlistment: The guarantee fee for the whole tenure must be paid up-front in one lump sum when the loan is enlisted, at 0.50% on the amount disbursed in the first year and on the outstanding principal at each year-end in the approved amortization schedule.
Page 3 · AnalysingCharge a full year's fee for a remaining part-year: For a remaining part of the tenure of less than one year, the fee must be calculated for a full year.
Page 3 · AnalysingDeposit the guarantee fee into the Credit Guarantee Fund account: The guarantee fee must be deposited online or by pay order into CGD's bank account named 'Credit Guarantee Fund'.
Page 3 · AnalysingRecover the guarantee fee from the borrower: The guarantee fee may be recovered from the borrower concerned.
Page 3 · AnalysingPay FICGS guarantee fees from own funds: Under the financial inclusion refinance scheme for Tk 10/50/100 account holders (FICGS), each PFI must pay the up-front guarantee fee from its own funds.
Page 3 · AnalysingPay up-front fee for tenure extended by rescheduling: When the tenure of an enlisted loan is extended by rescheduling/restructuring, an up-front fee at the rate in sub-paragraph (ka) must be paid on the outstanding principal for the extended period.
Page 3 · AnalysingPay up-front fee for tenure extended by renewal: When the tenure of an enlisted working capital loan is extended by renewal, an up-front fee at the rate in sub-paragraph (ka) must be paid on the renewed loan for the extended period.
Page 3 · AnalysingPay a 1% late fee for late Annexure-Ga: If Annexure-Ga is sent late, the PFI must pay a late fee of 1% of the total guarantee fee payable for that month.
Page 3 · AnalysingDo not recover the late fee from customers: The late fee must be paid from the PFI's own funds and must not be recovered from the customer in any way.
Page 3 · AnalysingPay fees on earlier guarantees at the guarantee-letter rate: Guarantee fees payable on loans guaranteed before this circular must be deposited with CGD at the rate stated in the loan's guarantee letter.
Page 4 · AnalysingRecord guaranteed loans as CGS in CIB reports: When reporting guaranteed loans to the Credit Information Bureau (CIB) under CIB Circular No. 02 dated 23 June 2024, the loans must be recorded as CGS.
Page 5 · AnalysingSubmit the quarterly performance statement (Annexure-Chha): The Quarterly Statement of Performance of Guaranteed Loan/Investment (Annexure-Chha) must be sent to CGD every quarter by the last working day of the following month.
Page 5 · AnalysingSubmit the quarterly debt recovery report (Annexure-Jha): The Quarterly Debt Recovery Report of Classified Loan/Investment (Annexure-Jha) must be sent to CGD every quarter by the last working day of the following month.
Page 5 · AnalysingSubmit the quarterly recovery statement for claim-settled loans (Annexure-Nya): The Quarterly Recovery Statement for Claim-Settled Loans/Investments (Annexure-Nya) must be sent to CGD every quarter by the last working day of the following month.
Page 5 · AnalysingSubmit the yearly PFI performance report (Annexure-Ja): The Yearly Performance Report of PFI (Annexure-Ja) must be sent to CGD by the last working day of February of the following year.
Page 5 · AnalysingFollow Bangladesh Bank instructions on loan disbursement and recovery: Instructions issued by Bangladesh Bank from time to time on loan/investment disbursement and recovery must be properly followed.
Page 5 · AnalysingFollow all instructions of this circular to get the guarantee: Banks and finance companies must follow all the instructions of this circular to get the credit guarantee facility.
Page 5 · AnalysingFollow the Manual of Credit Guarantee Scheme: The Manual of Credit Guarantee Scheme issued through SMESPD Circular No. 04/2020 and later related instructions must be followed.
Page 5 · AnalysingSettle pending actions under the repealed circulars by their rules: Any action taken under the repealed circulars that is pending or ongoing must be settled according to those circulars' instructions.
Page 5 · AnalysingSign a scheme-wise Participation Agreement with CGD: To get credit guarantee cover for collateral-free loans under the CMSME Tk 25,000 crore pre-finance scheme, the Tk 10/50/100 account holders refinance scheme, the women entrepreneurs small enterprise refinance fund and the agro-product processing refinance fund, the institution must sign a scheme-wise Participation Agreement with the Credit Guarantee Department.
Page 1 · AnalysingGuarantee for only one scheme and one loan type per borrower: A customer/entrepreneur may get credit guarantee cover under only one scheme and against only one of a working capital or a term loan/investment.
Page 1 · AnalysingNon-funded and contingent facilities are outside the guarantee: Non-funded or contingent-liability loans/investments must not be brought under this guarantee.
Page 1 · AnalysingGet CGD prior approval to enlist converted contingent liabilities: If a contingent liability turns into a funded loan (other than a forced loan/investment), it may be added to the guarantee portfolio only with prior approval from CGD.
Page 1 · AnalysingKeep guaranteed loans within the customer-level loan limits: To get guarantee cover, a customer-level loan/investment must be at least Tk 25,000 and must not exceed the scheme's maximum limit for the enterprise category set in the table; under FICGS the maximum is Tk 5 lakh for a single customer and, for group loans to groups of 2-5 members, Tk 4 lakh per member and Tk 20 lakh per group.
Page 2 · AnalysingSend the scheme-wise PGL demand to CGD by 15 January: Each Participating Financial Institution (PFI) must send its scheme-wise Portfolio Guarantee Limit (PGL) demand for the calendar year to CGD by 15 January.
Page 2 · AnalysingApply to CGD to raise the PGL once it is achieved: On achieving the set PGL, PFIs may apply to CGD to increase the limit.
Page 2 · AnalysingPGL only for PFIs with average classified loans of 20% or less: Only PFIs whose classified loan/investment ratio, averaged over 31 March, 30 June and 30 September of the year before the PGL year, is 20% or less are eligible for a PGL.
Page 2 · AnalysingReserve 10% of PGL for women entrepreneurs: For schemes other than the women entrepreneurs small enterprise refinance fund, PFIs must reserve 10% of their PGL for disbursement to women entrepreneurs.
Page 2 · AnalysingUse unused women's PGL share for others after the third quarter: Any unused part of the PGL reserved for women entrepreneurs at the end of the third quarter of the year may be used to guarantee loans to other entrepreneurs.
Page 2 · AnalysingEnlist loans after documentation under Annexures Ka and Kha: PFIs must follow their own loan/investment policy and guidelines, complete documentation according to the Credit Guarantee Registration Form (Annexure-Ka) and the Due Diligence and Documentary Checklist (Annexure-Kha), disburse the loan and then add it to the guarantee portfolio; the guarantee period starts on the disbursement date.
Page 2 · AnalysingGive each enlisted loan a unique guarantee registration number: At enlistment, PFIs must give each loan/investment a unique guarantee registration number.
Page 2 · AnalysingFollow the prescribed registration number format: The registration number must follow the format 'EDW FI ALIAS/EDW_FI_ID/Short_Title_of_CGS/PGL YEAR/Registration_Number'.
Page 2 · AnalysingSend the monthly portfolio registration summary (Annexure-Ga): PFIs must send CGD the scheme-wise Monthly Portfolio Guarantee Registration Summary for New Loan/Investment (Annexure-Ga) by the 15th of the following month.
Page 3 · AnalysingE-mail soft copies of new loan detail statements: Within the same time, PFIs must e-mail the soft copy (Excel file) of each enlisted New Loan/Investment Detail Statement listed in Annexure-Ga to [email protected].
Page 3 · AnalysingGet CGD prior approval to reschedule or restructure guaranteed term loans: PFIs must obtain prior approval from CGD before rescheduling or restructuring an enlisted term loan/investment.
Page 3 · AnalysingReport rescheduled/restructured loans in Annexure-Gha: After CGD's no-objection, PFIs must send details of rescheduled/restructured loans in the Statement of Rescheduling/Restructuring Term Loan/Investment (Annexure-Gha) to CGD in writing and as an Excel soft copy to [email protected] by the 15th of the following month; the loan stays under its original PGL and keeps its registration number.
Page 3 · AnalysingRenew guaranteed working capital loans within their tenure: An enlisted working capital loan/investment must be renewed within its existing tenure.
Page 3 · AnalysingComplete renewal of guaranteed working capital loans within 15 days: Although BRPD Circular No. 06 dated 25 June 2025 applies, the renewal process of a guaranteed working capital loan may be completed within the next 15 days.
Page 3 · AnalysingReport renewed working capital loans in Annexure-Umo: PFIs must send details of renewed working capital loans in the Statement of Renewal of Working Capital Loan/Investment (Annexure-Umo) to CGD in writing and as an Excel soft copy to [email protected] by the 15th of the following month; the loan stays under its original PGL and keeps its registration number.
Page 3 · AnalysingSubmit portfolio data online after automation: Once automation is complete, PFIs may submit the data of enlisted loans online through www.cgims.bb.org.bd.
Page 3 · AnalysingNo new guarantees while a scheme Participation Agreement is cancelled or suspended: If a PFI's participation agreement for a scheme with the SME and Special Programmes Department or the Financial Inclusion Department is cancelled or suspended, no new guarantee may be enlisted for that PFI under that scheme until the cancellation or suspension is withdrawn.
Page 3 · AnalysingInform CGD in writing when refinance is not given or is cancelled: If an enlisted loan is not included in, or loses, the related pre/refinance facility, its guarantee is treated as cancelled and the PFI must inform CGD in writing.
Page 3 · AnalysingPay the guarantee fee up-front for the full tenure at enlistment: The guarantee fee for the whole tenure must be paid up-front in one lump sum when the loan is enlisted, at 0.50% on the amount disbursed in the first year and on the outstanding principal at each year-end in the approved amortization schedule.
Page 3 · AnalysingCharge a full year's fee for a remaining part-year: For a remaining part of the tenure of less than one year, the fee must be calculated for a full year.
Page 3 · AnalysingDeposit the guarantee fee into the Credit Guarantee Fund account: The guarantee fee must be deposited online or by pay order into CGD's bank account named 'Credit Guarantee Fund'.
Page 3 · AnalysingRecover the guarantee fee from the borrower: The guarantee fee may be recovered from the borrower concerned.
Page 3 · AnalysingPay FICGS guarantee fees from own funds: Under the financial inclusion refinance scheme for Tk 10/50/100 account holders (FICGS), each PFI must pay the up-front guarantee fee from its own funds.
Page 3 · AnalysingPay up-front fee for tenure extended by rescheduling: When the tenure of an enlisted loan is extended by rescheduling/restructuring, an up-front fee at the rate in sub-paragraph (ka) must be paid on the outstanding principal for the extended period.
Page 3 · AnalysingPay up-front fee for tenure extended by renewal: When the tenure of an enlisted working capital loan is extended by renewal, an up-front fee at the rate in sub-paragraph (ka) must be paid on the renewed loan for the extended period.
Page 3 · AnalysingPay a 1% late fee for late Annexure-Ga: If Annexure-Ga is sent late, the PFI must pay a late fee of 1% of the total guarantee fee payable for that month.
Page 3 · AnalysingDo not recover the late fee from customers: The late fee must be paid from the PFI's own funds and must not be recovered from the customer in any way.
Page 3 · AnalysingPay fees on earlier guarantees at the guarantee-letter rate: Guarantee fees payable on loans guaranteed before this circular must be deposited with CGD at the rate stated in the loan's guarantee letter.
Page 4 · AnalysingRecord guaranteed loans as CGS in CIB reports: When reporting guaranteed loans to the Credit Information Bureau (CIB) under CIB Circular No. 02 dated 23 June 2024, the loans must be recorded as CGS.
Page 5 · AnalysingSubmit the quarterly performance statement (Annexure-Chha): The Quarterly Statement of Performance of Guaranteed Loan/Investment (Annexure-Chha) must be sent to CGD every quarter by the last working day of the following month.
Page 5 · AnalysingSubmit the quarterly debt recovery report (Annexure-Jha): The Quarterly Debt Recovery Report of Classified Loan/Investment (Annexure-Jha) must be sent to CGD every quarter by the last working day of the following month.
Page 5 · AnalysingSubmit the quarterly recovery statement for claim-settled loans (Annexure-Nya): The Quarterly Recovery Statement for Claim-Settled Loans/Investments (Annexure-Nya) must be sent to CGD every quarter by the last working day of the following month.
Page 5 · AnalysingSubmit the yearly PFI performance report (Annexure-Ja): The Yearly Performance Report of PFI (Annexure-Ja) must be sent to CGD by the last working day of February of the following year.
Page 5 · AnalysingFollow Bangladesh Bank instructions on loan disbursement and recovery: Instructions issued by Bangladesh Bank from time to time on loan/investment disbursement and recovery must be properly followed.
Page 5 · AnalysingFollow all instructions of this circular to get the guarantee: Banks and finance companies must follow all the instructions of this circular to get the credit guarantee facility.
Page 5 · AnalysingFollow the Manual of Credit Guarantee Scheme: The Manual of Credit Guarantee Scheme issued through SMESPD Circular No. 04/2020 and later related instructions must be followed.
Page 5 · AnalysingSettle pending actions under the repealed circulars by their rules: Any action taken under the repealed circulars that is pending or ongoing must be settled according to those circulars' instructions.
Page 5 · AnalysingIslamic Shariah-based institutions may take the guarantee under this policy: Islamic Shariah-based banks and finance companies may take the guarantee facility under this policy when providing investments under the credit guarantee facilities.
Page 5 · AnalysingIslamic Shariah-based institutions may take the guarantee under this policy: Islamic Shariah-based banks and finance companies may take the guarantee facility under this policy when providing investments under the credit guarantee facilities.
Page 5 · Analysing
Who it applies to
All scheduled banks in Bangladesh
Page 1 · AnalysingNon-bank financial institutions
Page 1 · AnalysingIslamic Shariah-based banks
Page 5 · Analysing
Dates
Effective: 2026-01-01
Page 5 · Analysing
Exceptions
Banks and finance companies that already signed a participation agreement with CGD under these schemes need not sign a new one.
Page 1 · Analysing
Related circulars
- ACD-1 Circular Letter No. 05/202619 November 2026 Ready
Agricultural and Rural Credit Policy and Program for the FY 2026-2027
- BRPD-1 Circular Letter No. 40/202619 November 2026 Ready
Proper Implementation of Stimulus Schemes of BDT 60,000 (Sixty Thousand) Crore Announced by Bangladesh Bank.
- BRPD-1 Circular No. 16/202630 August 2026 Ready
Pre-Finance Scheme for Export-oriented Frozen Food Sector
- BRPD-1 Circular No. 15/202630 July 2026 Ready
Pre-Finance scheme for the Growth and Development of Leather and Leather Goods Industry Sector
- BRPD-1 Circular Letter No. 25/202629 July 2026 Ready
Regarding withdrawal of case filed by customer before receiving policy Support.
- BRPD-3 Circular Letter No. 01/20267 July 2026 Ready
Pre Finance Scheme to Support the Closed Industry and Service Sectors
- ACD-1 Circular No. 02/20266 July 2026 Ready
Refinance Scheme of Tk 3,000 Crore for Creating Agricultural Based Economic Hub in North Bengal of the Country
- ACD-1 Circular Letter No. 02/20261 July 2026 Ready
Formulation of Bangladesh Bank Agricultural Development Common Fund (BBADCF)
Source: Bangladesh Bank. Each point links to the page of the original circular it comes from. All CGD circulars