Guidance for banks in implementing IFRS 9 Financial Instruments.
বিআরপিডি সার্কুলার নং ০৬/২০২৬
Summary
Under the IFRS 9 roadmap in BRPD Circular Letter 03/2025, Bangladesh Bank issues minimum-requirement guidance for scheduled banks implementing IFRS 9, under section 49(1)(cha) BCA.
Page 1 · AnalysingThe guidance applies to credit facilities by January 2028 and to other financial instruments by January 2029; the Board-approved ECL framework is due to BB by 15 July 2026.
Page 1 · ReadyIt sets governance, default, staging, SICR (30-day backstop), forbearance, write-off, measurement (5-year data, FLI, quarterly ECL), model testing and annual independent validation.
Page 13 · ReadyBanks must file quarterly ECL movement statements within 30 days, keep the higher of ECL and regulatory provision through a Loan Loss Reserve, and may phase in the Day 1 CET1 impact over 5 years.
Page 27 · Ready
What has changed
ECL-based provisioning framework replaces sole reliance on regulatory provisioning, with a regulatory floor via Loan Loss Reserve.
Page 27 · AnalysingNew reporting: ECL framework by 15 July 2026, quarterly ECL statements, validation results.
Page 16 · Ready
Requirements
Apply the IFRS 9 Implementation Guidance to credit facilities by January 2028: Banks must apply the Implementation Guidance (as minimum requirements for IFRS 9) to funded and non-funded credit facilities by January 2028.
Page 1 · ReadyApply the Guidance to other financial instruments by January 2029: The Guidance must be applied to all other IFRS 9 financial instruments, such as investment securities, by January 2029.
Page 1 · ReadyAdopt the BCBS guidance on credit risk and ECL: Banks are recommended to adopt the principles of the Basel Committee's December 2015 guidance on credit risk and accounting for expected credit losses.
Page 1 · AnalysingCorrespond with BB only from a dedicated official email: For implementation guidance and clarification, banks should correspond with Bangladesh Bank only from a dedicated official email.
Page 2 · AnalysingForeign bank branches: local ownership of the ECL framework: Foreign banks may apply the Head Office/Group ECL framework, but must apply it in the Bangladesh context, with a local team under key management that owns it and is accountable for the minimum standards.
Page 12 · ReadyBoard-approved ECL framework reviewed at least annually: Every bank must have a documented, Board-approved ECL framework, referenced in its credit risk policies and reviewed and updated at least annually.
Page 12 · ReadyCredit risk governance structure for ECL: Banks must maintain a credit risk governance structure for ECL with segregation of duties, escalation lines and independent model oversight, described in the ECL framework with Board, senior management, risk management and audit roles.
Page 13 · ReadyIndependent risk function oversight of ECL: The risk management function should give independent oversight of ECL; if it helped develop the framework, the review must go to another control function; it needs unfettered access and must report independently to senior management and the Board.
Page 15 · ReadySubmit the Board-approved ECL framework to BB by 15 July 2026: An initial copy of the Board-approved ECL framework must be submitted to Bangladesh Bank no later than 15 July 2026.
Page 16 · AnalysingSubmit framework updates within 60/30 days: Periodic Board-approved updates of the ECL framework must be submitted to BB within 60 days of period-end, and interim updates within 30 days.
Page 16 · AnalysingMinimum contents of the ECL framework: The ECL framework must set out default definition (90+ days past due or credit-impaired, plus unlikeliness-to-pay indicators), staging and upgrading criteria, SICR criteria, impairment triggers, forbearance treatment, write-off and recovery criteria, and the ECL measurement framework.
Page 16 · ReadyAnnual review of internal ratings, SICR criteria and impairment triggers: The internal credit rating methodology, SICR criteria and impairment triggers must be reviewed at least annually.
Page 18 · ReadyStaging rules and contagion: Exposures are staged account by account unless borrower factors require one stage; contagion (including from exposures at other banks) must be assessed; exposures whose SICR cannot be assessed go to Stage 2.
Page 17 · ReadyUpgrading conditions: Upgrades must be done by a department independent of credit review, only after arrears are fully repaid, deterioration factors are gone and 90 days of satisfactory performance, with documented assessments for supervisory review.
Page 18 · AnalysingSICR 30-day backstop and default-risk basis: SICR is presumed at 30 days past due; a longer threshold must be justified with documented evidence; SICR must be based on default risk, not loss, and collateral must not be considered unless the exposure is collateral-dependent.
Page 20 · ReadyImpairment testing on triggers: A trigger must lead to an impairment test, and results must be kept for supervisory review.
Page 20 · AnalysingForbearance staging and limits: Forborne Stage 1 exposures move to Stage 2; forborne Stage 2 exposures are tested for impairment as if not forborne; exit needs 12 months of satisfactory performance; the number of forbearances must be limited per BB directives and documented.
Page 21 · ReadyWrite off when no reasonable expectation of recovery: Banks should write off exposures, in whole or in part, when there is no reasonable expectation of recovery, under documented write-off and recovery criteria.
Page 21 · ReadyAppropriate ECL measurement methodology: Banks must adopt, document and implement an ECL measurement methodology proportionate to their portfolios, with defined model inputs and documented measurement.
Page 22 · ReadyAt least 5 years of historical data; quarterly data review: Banks must use at least 5 years of historical credit risk data; proxies must be documented and temporary; credit data must be updated and reviewed at least quarterly.
Page 22 · ReadyManagement must understand models, including outsourced ones: Whether models are built internally, procured or adopted from a parent, banks must have the expertise to implement and challenge them, customise them to local data, and management must understand and explain the methodology.
Page 23 · ReadyManagement overlays approved by the Board: Management overlays must be reasonable, documented for supervisory review and approved by the Board, with materiality criteria in the ECL framework.
Page 23 · ReadyModel assumptions and forward-looking information: Assumptions must be unbiased, documented and reviewed at least annually; inputs must reflect forward-looking information with documented macroeconomic variables and sources, with source changes justified and FLI relevance assessed at least quarterly.
Page 24 · ReadyAt least three scenarios under probability weighting: Banks using probability-weighted ECL should consider at least three scenarios with documented probabilities.
Page 24 · ReadyGroup-based estimation on shared risk characteristics: Groups must share credit risk characteristics, which are reviewed periodically, and groups must be adjusted where they no longer apply.
Page 24 · AnalysingEstimate ECL at least quarterly: Banks must estimate ECL quarterly or more often.
Page 25 · ReadyAnnual model performance tests: Model performance tests must be run at least annually against documented benchmarks, with results shared with the Board, acted on, and available for supervisory review.
Page 25 · ReadyAnnual independent model validation; first by 2027: Model frameworks must be validated at least annually, with the first validation after initial development within 2027; validators must be competent, uninvolved in development and contractually accountable to BB.
Page 25 · AnalysingNotify BB before engaging model validators: Banks must notify BB before engaging model validators, with evidence of competence, so BB can object.
Page 26 · AnalysingValidation results, action plan and progress reports: Validation results must be shared with the Board and submitted to BB by validators within 30 days; banks have 30 more days to submit a remediation plan and must submit periodic progress reports.
Page 26 · ReadyInterest recognition by stage: Interest on Stage 1 and 2 exposures must be recognised on the gross carrying amount, and on Stage 3 on the net carrying amount.
Page 27 · ReadyIFRS 7 disclosures: Banks must comply with IFRS 7 disclosure requirements.
Page 27 · AnalysingQuarterly ECL movement statement within 30 days: Banks must submit a statement of changes in opening and closing ECL allowances (Annex E) to BB within 30 days after each quarter, showing stage movements, write-offs, recoveries and model adjustments.
Page 27 · ReadyReconcile ECL allowance with regulatory provisions: Banks must submit a reconciliation of the ECL allowance to regulatory provisions (Annex F) to identify additional regulatory provisions calculated under section 9.
Page 27 · ReadyKeep the higher of ECL and regulatory provision via Loan Loss Reserve: Banks must keep the higher of the IFRS 9 ECL allowance and the regulatory provision under BRPD Circular 15; any shortfall goes to a non-distributable Loan Loss Reserve, not expensed, with reductions transferred to retained earnings.
Page 27 · AnalysingOptional 5-year transitional amortisation of Day 1 impact: Banks may amortise the Day 1 IFRS 9 ECL impact on CET1 over 5 years using a static approach; those opting out at adoption may not adopt it later.
Page 28 · ReadyRegulatory treatment of ECL provisions and capital disclosure: Stage 1-2 ECL counts as general provisions and Stage 3 as specific provisions; banks must disclose capital with and without transitional adjustments and base capital ratios and decisions on post-adjustment CET1.
Page 28 · Ready
Who it applies to
All scheduled banks in Bangladesh
Page 1 · Ready
Dates
Effective: 2026-03-08
Page 1 · ReadyReporting: 2026-07-15
Page 16 · Ready
Related circulars
- BRPD Circular Letter No. 03/202523 January 2025 Ready
Implementation of ECL-based Loan Classification and Provisioning under IFRS 9.
- BRPD-1 Circular Letter No. 27/202610 August 2026 Ready
Deduction of source tax at the applicable rate on interest/profit paid on deposits in accordance with the Income Tax Act, 2023 and timely deposit thereof into the Government Treasury.
- BRPD-2 Circular Letter No. 05/20262 April 2026 Ready
Submission of Interim Report to Bangladesh Bank
- BRPD-1 Circular No. 05/20263 March 2026 Ready
Instructions to be Followed in Case of Continuous Loan Renewal.
- BRPD Circular Letter No. 29/202521 December 2025 Ready
Loan Classification and Provisioning
- BRPD Circular Letter No. 22/202513 October 2025 Ready
Loan Classification and Provisioning.
- BRPD Circular No. 05/202525 June 2025 Ready
Master Circular: Loan Classification and Provisioning
- BRPD Circular No. 14/201223 September 2012 Ready
Master Circular: Loan Classification and Provisioning
Source: Bangladesh Bank. Each point links to the page of the original circular it comes from. All BRPD circulars